ACMOSS programme
The Critical Communications Review · Programme Tracker
France: Réseau Radio du Futur (RRF)
Tracking ACMOSS's Réseau Radio du Futur, the nationwide 4G/5G mission-critical broadband service for France's security, emergency and health services, which succeeds the INPT, Rubis and Antares narrowband networks.
RRF services were launched in November 2025, after a construction phase completed at the end of 2024. ACMOSS's website now targets 300,000 users in 2028, against an original 2027 target; deployment is under way with police, fire, SAMU and armed forces users.
Programme timeline, 2017–2031
Filled markers are milestones already reached; open markers are published plans and targets. Steps without a published date appear only in the milestone log. Hover over or tap a marker for detail; on mobile, scroll the chart sideways.
● Completed ○ Planned ○ Target
Original departmental rollout schedule
The 2024 plan set out deployment across 97 departments in three waves. Service launch later moved from April to November 2025, and ACMOSS has not published updated wave figures.
Source: Banque des Territoires, reporting ACMOSS, 2024.
Plan versus reality
How the published schedule has moved since the programme started.
| Item | Original plan | Latest position | Source |
|---|---|---|---|
| Service launch | Early 2024, ahead of the Paris Olympic Games | Launched November 2025 | Banque des Territoires – 2024 |
| 300,000 users | 2027 | 2028 (ACMOSS website); 2029 in the Director’s May 2026 mission | ACMOSS – Key figures |
| Departmental rollout | 43 / 30 / 24 departments in 2025 / 2026 / 2027 | Rollout initiated November 2025; 100+ membership agreements by end-2025 | CCR ACMOSS in 2025 (Jan 2026) |
Milestone log
Every dated event behind the timeline. Entries marked “CCR” link to coverage in The Critical Communications Review.
| When | Track | Milestone | Status | Source |
|---|---|---|---|---|
| 2017 | Programme | President of the Republic announces a new shared radio network for security and rescue services | ● Completed | Maire-info – April 2023 |
| Sep 2022 | Contracts | Bouygues Telecom appointed by the Ministry of the Interior to contribute to the RRF programme | ● Completed | CCR Bouygues Telecom and ACMOSS (Oct 2025) |
| Oct 2022 | Contracts | Consortium led by Airbus and Capgemini selected as Package 2 integrator | ● Completed | CCR Airbus/Capgemini selected (Oct 2022) |
| Jan 2023 | Programme | Interior Ministry programming law (LOPMI) provides for a State agency to build and run the RRF | ● Completed | Maire-info – April 2023 |
| Mar 2023 | Programme | Decree creates ACMOSS, the agency responsible for the RRF | ● Completed | Maire-info – April 2023 |
| Oct 2023 | Adoption | 140 RRF terminals and 3 dispatch positions deployed at the national firefighters’ congress in Toulouse | ● Completed | CCR RRF terminals at CNSPF (Oct 2023) |
| End 2024 | Network | Construction of the RRF completed | ● Completed | CCR ACMOSS in 2025 (Jan 2026) |
| May 2025 | Adoption | SDIS de l’Oise among the first fire and rescue services to join the RRF | ● Completed | CCR SDIS de l’Oise joins RRF (May 2025) |
| Jun 2025 | Network | Regular Service Verification (VSR) begins with about 800 users in four departments | ● Completed | Acteurs publics – Nov 2025 |
| Jul 2025 | Adoption | Ministry of the Armed Forces signs its RRF membership agreement | ● Completed | CCR Armed Forces join RRF (Jul 2025) |
| Oct 2025 | Network | Bouygues Telecom 4G/5G RAN goes live for the RRF alongside Orange; Rapid Response Solutions partnership | ● Completed | CCR Bouygues Telecom and ACMOSS (Oct 2025) |
| Nov 2025 | Network | Verification completed; RRF services launched and nationwide rollout initiated | ● Completed | CCR ACMOSS in 2025 (Jan 2026) |
| Dec 2025 | Adoption | More than 100 RRF membership agreements signed | ● Completed | CCR ACMOSS in 2025 (Jan 2026) |
| Jan 2026 | Programme | ACMOSS publishes its first Objectives and Performance Contract for 2026–2030 | ● Completed | CCR ACMOSS 2026–2030 strategy (Jan 2026) |
| Apr 2026 | Network | Bouygues Telecom delivers first Rapid Response Solution equipment (deployable base station with satellite backhaul) | ● Completed | CCR Rapid Response Solution (Apr 2026) |
| May 2026 | Programme | Rémi de Gouvion Saint-Cyr takes office as Director of ACMOSS | ● Completed | CCR New ACMOSS Director (May 2026) |
| May 2026 | Network | Operational testing of the RRF in the Rennes metro network | ● Completed | CCR Rennes metro testing (May 2026) |
| Aug 2026 | Adoption | RATP security teams trial around 50 RRF smartphones in pre-deployment | ● Completed | CCR RATP pre-deployment (Aug 2026) |
| Sep 2026 | Adoption | Paris Fire Brigade (BSPP) begins first RRF deployment phase, initially for Grand Paris Express line 15 South | ● Completed | ACMOSS – Paris Fire Brigade (Nov 2026) |
| Sep 2026 | Adoption | SDIS of Cher, Sarthe and Yvelines, three SAMU services, a hospital and a municipal police force sign up | ● Completed | CCR New services sign up (Sep 2026) |
| Oct 2026 | Adoption | SDIS 74 and Haute-Savoie Departmental Council sign declaration of commitment to deploy the RRF | ● Completed | CCR Haute-Savoie commitment (Oct 2026) |
| Oct 2026 | Adoption | RRF launch meeting held at the Vienne prefecture in Poitiers | ● Completed | ACMOSS – Vienne (Oct 2026) |
| Oct 2026 | Adoption | French Navy prepares naval-base trial; Ministry of the Armed Forces rolling out RRF across metropolitan France | ● Completed | CCR French Navy engagement (Oct 2026) |
| Oct 2026 | Adoption | SAMU and SMUR progressively join the RRF, with subscriptions and equipment funded by the Ministry of Health | ● Completed | ACMOSS – SAMU and SMUR (Oct 2026) |
| Oct 2026 | Europe | ACMOSS presents the RRF in Brussels as a reference for the EU Critical Communication System (EUCCS) | ● Completed | CCR RRF and EUCCS (Oct 2026) |
| Oct 2026 | Adoption | SDIS 37, 38, 39, 61 and 78, five SAMU, the City of Blois and the Cher department sign membership agreements | ● Completed | ACMOSS – New members (Oct 2026) |
| Nov 2026 | Adoption | Rhône: first prefecture to sign; national police deploying 3,000 RRF SIM cards in the department | ● Completed | ACMOSS – Rhône (Nov 2026) |
| 2028–2029 | Network | RRF rollouts in further metropolitan transport networks | ○ Planned | CCR Rennes metro testing (May 2026) |
| 2028 | Adoption | 300,000 users of security and emergency services on the RRF (ACMOSS website; “by 2029” in the Director’s May 2026 mission) | ○ Target | ACMOSS – Key figures |
| 2030 | Programme | End of the 2026–2030 Objectives and Performance Contract period | ○ Planned | CCR ACMOSS 2026–2030 strategy (Jan 2026) |
Supply chain and partners
Principal industrial partners named in public announcements.
| Organisation | Role | Source |
|---|---|---|
| Airbus and Capgemini | Package 2 integrator; Airbus provides the SYRIUS critical communications application | CCR Airbus/Capgemini selected (Oct 2022) |
| Orange | Radio access network with prioritised access for RRF users | CCR ACMOSS in 2025 (Jan 2026) |
| Bouygues Telecom | Radio access network (live October 2025) and Rapid Response Solutions | CCR Bouygues Telecom and ACMOSS (Oct 2025) |
| SFR and Free | National roaming for RRF users | CCR ACMOSS in 2025 (Jan 2026) |
| Atos | Information and management system (SI-G), the RRF administration portal | Atos |
| Eutelsat OneWeb | Satellite backhaul for Rapid Response Solution deployable base stations | CCR Rapid Response Solution (Apr 2026) |
About this tracker
Compiled by The Critical Communications Review from its own coverage of ACMOSS and the RRF, ACMOSS’s official website (acmoss.fr), and French official and trade press sources. Last reviewed 9 November 2026.
Future dates are ACMOSS plans and targets as published or reported, and are subject to change. The programme cost of €896 million for 2022–2030 was reported by Secours Mag in 2025; the €345 million initial State funding for 2020–2026 was reported by Maire-info and Banque des Territoires.
Can you add to this tracker? Anyone who believes they can provide valuable information is welcome to share it with The Critical Communications Review by e-mail at info@mcc-resources.com.