Tracking ASTRID, the operator of Belgium’s nationwide TETRA network for the emergency and security services since 1998, and its NextGenCom programme to introduce mission-critical broadband.

ASTRID plans a hybrid network that combines its own core and radio systems with commercial mobile networks. The 5G network was announced for early 2027, with a gradual move away from TETRA from around 2028. TETRA terminals will be supported until at least 2030 and no switch-off date has been set.

5G network
Early 2027
As announced in 2023
TETRA transition
From ~2028
Gradual, based on operational readiness
TETRA terminals supported
To 2030+
Until at least 2030 · ASTRID, 2025
Users
70,000+
In about 750 organisations · 2018
Management contract
2023–2027
Fourth contract between the State and ASTRID
TETRA midlife upgrade
€60m
Completed at the end of 2019

Programme timeline, 2014–2030

Filled markers are milestones already reached; open markers are published plans and targets. Steps without a published date appear only in the milestone log. Hover over or tap a marker for detail; on mobile, scroll the chart sideways.

● Completed   ○ Planned   ○ Target

Policy
●●●○Nov 2026
TETRA network
●●○○
Blue Light Mobile
●●●●●●
NextGenCom
●●●●○
Europe
●●●
 
201420162018202020222024202620282030
 

Plan versus reality

How the published schedule has moved since the programme started.

ItemOriginal planLatest positionSource
Mission-critical broadband 3GPP mission-critical services over commercial operators around 2025 (ASTRID roadmap, 2017) Hybrid network with ASTRID’s own core; 5G network announced for early 2027 CCR 5G network planned for 2027 (Aug 2023)
TETRA Gradual changeover from TETRA during 2025–2030 (2018) Transition from around 2028; terminals supported to at least 2030; no end date set Critical Communications Today – interview (Jun 2025)
Network model Operator model on commercial networks (2018) Hybrid model combining ASTRID’s dedicated core and radio access with selected public network components Critical Communications Today – interview (Jun 2025)

Milestone log

Every dated event behind the timeline. Entries marked “CCR” link to coverage in The Critical Communications Review.

WhenTrackMilestoneStatusSource
Apr 2014 Blue Light Mobile Blue Light Mobile broadband data service launched over three Belgian commercial networks ● Completed CCR Blue Light Mobile launched (Apr 2014)
Oct 2017 Blue Light Mobile Next generation of Blue Light Mobile launched ● Completed CCR Blue Light Mobile, next generation (Oct 2017)
Oct 2018 Policy Decision announced to move the emergency services from TETRA to an operator model based on 5G technology ● Completed CCR Switch to 5G announced (Oct 2018)
Aug 2019 TETRA network Airbus–Proximus consortium awarded a long-term support and maintenance contract ● Completed CCR Airbus–Proximus maintenance contract (Aug 2019)
End 2019 TETRA network Eight-year, €60 million midlife upgrade of the radio and paging systems completed ● Completed CCR Midlife upgrade completed (Apr 2020)
Jul 2020 Europe ASTRID signs the BroadWay prototype contracts as lead procurer ● Completed CCR BroadWay prototype phase (Jul 2020)
May 2022 NextGenCom ASTRID sets out plans for a new hybrid 5G network, with TETRA kept in service until it is ready ● Completed CCR ASTRID prepares the future (May 2022)
Jan 2023 Blue Light Mobile Number of Blue Light Mobile users reported to have more than doubled in a few years ● Completed CCR Blue Light Mobile users doubled (Jan 2023)
Apr 2023 Blue Light Mobile 5G option available on all Blue Light Mobile subscriptions ● Completed CCR 5G for Blue Light Mobile (Apr 2023)
Aug 2023 Policy Council of Ministers approves the fourth management contract, allowing development of the 5G network to start ● Completed CCR 5G network planned for 2027 (Aug 2023)
Nov 2024 Blue Light Mobile Major development of the Blue Light Mobile service announced ● Completed CCR Blue Light Mobile development (Nov 2024)
Dec 2024 Europe Teltronic to provide MCX services for ASTRID under the EUCCS Preparation programme ● Completed CCR Teltronic and EUCCS (Dec 2024)
Jun 2025 Europe ACMOSS and ASTRID exchange experience on implementing mission-critical broadband ● Completed CCR ACMOSS and ASTRID (Jun 2025)
Jun 2025 NextGenCom ASTRID’s director general confirms a gradual TETRA transition from around 2028, as Brussels hosts Critical Communications World ● Completed Critical Communications Today – interview (Jun 2025)
Jan 2026 Policy ASTRID stresses its long-term public role and sovereign control of critical communications ● Completed CCR Public role and sovereignty (Jan 2026)
Early 2026 NextGenCom Users’ Advisory Committee workshop gathers operational requirements for NextGenCom ● Completed CCR Users’ Advisory Committee (Mar 2026)
Jul 2026 NextGenCom User committee reviews NextGenCom devices that combine TETRA-style robustness with smartphone ease of use ● Completed CCR NextGenCom devices (Jul 2026)
Oct 2026 Blue Light Mobile eSIM introduced for Blue Light Mobile subscribers ● Completed CCR eSIM for Blue Light Mobile (Oct 2026)
Early 2027 NextGenCom 5G network expected to be available ○ Planned The Brussels Times (Sep 2023)
End 2027 Policy Fourth management contract period ends ○ Planned Critical Communications Today – interview (Jun 2025)
Around 2028 TETRA network Gradual transition from TETRA to broadband begins ○ Target Critical Communications Today – interview (Jun 2025)
2030 TETRA network TETRA terminals supported until at least this date ○ Target Critical Communications Today – interview (Jun 2025)
No date TETRA network Switch-off of the TETRA network; ASTRID says it depends on operational readiness ○ No date set Critical Communications Today – interview (Jun 2025)

Supply chain and partners

Principal industrial partners named in public announcements.

OrganisationRoleSource
Airbus–Proximus consortium Long-term support and maintenance of the ASTRID network CCR Airbus–Proximus maintenance contract (Aug 2019)
Belgian commercial mobile operators Radio access for the Blue Light Mobile priority service CCR Blue Light Mobile launched (Apr 2014)
Teltronic MCX services for ASTRID within the EUCCS Preparation programme CCR Teltronic and EUCCS (Dec 2024)

About this tracker

Compiled by The Critical Communications Review from its own coverage of ASTRID, interviews with ASTRID’s management in Critical Communications Today, The Brussels Times and ASTRID presentations to PSCE. Last reviewed 10 November 2026.

ASTRID has not published the suppliers or a detailed schedule for NextGenCom in the sources reviewed, and the early-2027 date for the 5G network dates from 2023. No TETRA switch-off date has been set; it is shown as “No date set”.

Can you add to this tracker? Anyone who believes they can provide valuable information is welcome to share it with The Critical Communications Review by e-mail at info@mcc-resources.com.